| Slope Ratio | Span of Roof | Run of Rafter | Number of Units of Run | Unit of
Topic 14 – Intersecting Roof Components and Calculating Valley Rafters and Ridge
Topic 17 – Dormers
Topic 18 – Framing Intersecting Roofs in Metric
Topic 3 – Renovating Exterior Walls, Roof, Interior Finishes
Performs Site Layout
Site Layout Review Questions
Math Checkup: Converting Linear Measurements in Imperial and Metric
Take Rod Readings and Calculate Elevations Review Questions
Take Rod Readings and Calculate Elevations
Study Tips: Create a Glossary
Installs Engineered Floor Systems and Sheathing
Study Tips: Create a Summary from a Lecture
Math Checkup: Convert Feet and Inches to Decimal Feet
Focus On Self: About Your Brain
Constructs Footing, Formwork, and Installs Piles
Insulated Concrete Forms
Backfilling
Wall Formwork for Commercial Construction
Installs Concrete, Cement based, and Epoxy Products
Places Concrete Review Questions
Mixing and Testing Concrete
Math Checkup: Convert Decimal Feet to Feet and Inches
Interpret Project Drawings
Identify Residential Drawings
Interpret Building Codes
Maintains Hand, Power and Pneumatic Tools
Describe Types of Hammers and their Use
Identify, Use, and Maintain Planes
Identify the Procedures for Operating Portable Drills
Identify Procedures for Operating Portable Sanders
Operate Routers
Study Tips: SQ4R Method
Operate the Jointer and Planer
Review Questions Jointer and Planer
Powder Actuated Tools
Installs Materials, Fastners, Adhesives, and Connectors
Identify Engineered Wood Products
Solid and Hollow Wall Anchors
Expansion Anchors
Requirements for Fire and Sound Resistane: Permeance of Materials, Degree Days a
Describe Procedures of Insulating and Air/Vapour Sealing in Building Walls and C
Location of Air/Vapour Barrier
Installs Foundation Protection
Math Checkup: Converting Units of Area and Volume
Uses Stationary Access Equipment
Uses Mobile Access Equipment
Describe How to Construct and Use Wooden Scaffolding
Describe How to Assemble and Use Metal Scaffolding
Focus on Self: Automatic Thoughts
Uses Personal Protective Equipment and Safety Equipment
Eye and Respiratory Protection
Fall Protection
Review Questions Safe Work Environment
Chapter B1 – Interprets Project Drawings
Topic 1 – Types of Views, Lines, and Symbols
Topic 2 – Identify Types of Drawings
Topic 5 – Interpret Building Codes
Topic 1 – Commercial Specifications
Chapter B4 – Performs Site Preparation
Topic 1 – Establish Elevations with a Builder’s Level
Topic 2 – Take Rod Readings and Calculate Elevations
Topic 3 – Site Investigation and Building Layout with Hand Tools
Chapter B7 Performs Site Layout
Topic 5– Use a Trigonometry in Building Layout
Section 3D – Constructs Wall Systems
Topic 2 – Layout Exterior Wall Plates
Topic 5 – Install Backing and Blocking
Section 3E – Installs Exterior Finishes
Chapter E8 – Installs Exterior Wall Components
Topic 2 – Construct Metal Cornices
Topic 3 – The Rain Screen Principle
Topic 2 – Apply Hardboard and Vinyl Siding
Chapter E9 – Installs Exterior Wall Coverings
Calculating Percentages
Chapter E1 – Installs Exterior Jambs/Frames
Topic 3 – Construct Exterior Door Frame
Chapter E3 – Installs Specialty Exterior Doors
Chapter E4 – Installs Exterior Windows
Chapter E5 – Installs Exterior Door Hardware
The Proportion Equation
Section 4 – Constructs Roof and Ceiling Systems
Topic 2 – Gable Roof Components and Calculations
Topic 3 – Laying out a Common Rafter and Ridge Board
Topic 5 – Gable Ends, Studs, and Ladders
Topic 6 – Shed Roof Rafters
Topic 7 – Calculating Gable Roofs Using Metric
Section 2 – Installs Roofing
Chapter E6 – Installs Roofing Components
Chapter E7 – Installs Roof Coverings
Topic 3 – Apply Sheet Metal Roofing
Chapter C10 – Installs Grout and Repairs Concrete
Topic 1 – Commercial Specifications
Mixed Roofing Questions
Topic 8 – Ridge Boards and Hip Rafters
Topic 10 – Calculate Hip Roofs Using Metric Measurements
« Previous
Reading progress:
71%
Next »
Solid and Hollow Wall Anchors
Solid and Hollow Wall Anchors
Topic 5 – Solid and Hollow Wall Anchors
Anchor bolts
embedded into concrete as is it is still fluid. They are set at specific intervals and must be of minimum diameter and embedment according to their application. They are typically irregularly shaped or contain a bend to prevent them from turning during fastening after the concrete is set.
While the placement of anchor bolts is crucial, there are methods to allow movement of the bolt after the foundation has been placed. Methods include using sleeves to leave a void around the bolt and grouting an anchor bolt in a pocket that has been formed out (see below).
Anchor bolts are also referred to as “cast-in-place” anchors. This method of placing bolts in concrete as it is setting is the most effective and economical method of fastening materials to foundations. The drawback, however, is that its placement must be extremely accurate as they are unable to be moved. Any errors in placement will render the anchors useless.
Concrete Inserts
Another method of securing material down to concrete is through the use of cast-in-place inserts. The contain a threaded female end which sits flush with the top of the concrete. After the concrete is set, bolts are fastened into it.