Understanding Scrum

Asked 2010-06-24T14:55:56.340
14

I have been working as a .net developer following the waterfall model. When working on, say a 12 months project, usually my team follows Analysis, Design, Coding and Testing phases. But when it comes to following the Scrum process, I don't really understand how I need to deal with it.

Consider a sprint for 4 weeks and the backlog has 10 items. Let the sprint start now. If developers are working on some backlog items for the first 10 days, I don't know if testing (both SIT and UAT) will require JUST the remaining 10 days to complete the work. And now our sprint does not have any time to do last minute bug fixes and only few bugs could be fixed IN THE PLANNED SPRINT.

And when we do development, how can we make sure that we keep the testing team busy apart from just preparing test cases and waiting for us to deliver the functionality?

This raises a question if we need to deliver the first task/feature within the first 3 days of the sprint, so that testers might be ready with their test cases to test that piece.

I also need to educate my client to help in adapting the Scrum process.

I need some guidelines, references or a case study to make sure that our team follows a proper Scrum process. Any help would be appreciated.

Edit
Report

2 Answers

7

You definitely don't want to do all development in the first half of the sprint and all testing in the second half. That's just a smaller waterfall.

Your stories and tasks should be broken up into very small, discrete pieces of functionality. (It may take a while to get used to doing this, especially if the software you're working on is a monolithic beast like a previous job of mine that moved to using scrum.) At the beginning of the sprint the testers are developing their tests and the developers are developing their code, and throughout the sprint the tasks and stories are completed and tested. There should be fairly constant interaction between them.

The end of the sprint may feel a bit hectic while you're getting used to the methodology. Developers will feel burdened while they're working on the rest of the code and at the same time being given bugs to fix by the testers. Testers will grow impatient because they see the end of the sprint looming and there's still code that hasn't been tested. There is a learning curve and it will take some getting used to, the business needs to be aware of this.

It's important that the developers and testers really work together to create their estimates, not just add each other's numbers to form a total. The developers need to be aware that they can't plan on coding new features up until the last minute, because that leaves the testers there over the weekend to do their job in a rush, which will end up falling back on the developers to come in and fix stuff, etc.

Some tasks will need to be re-defined along the way. Some stories will fail at the end of the sprint. It's OK, you'll get it in the next sprint. The planning meeting at the start of each sprint is where those stories/tasks will be defined. Remember to be patient with each other and make sure the business is patient with the change in process. It will pay off in the long run, not in the first sprint.

answered 2010-06-24T15:07:47.563
4

A Scrum team is usually cross-functional, which means that the entire team is responsible for building completed pieces of functionality every Sprint. So if the QA testers did not finish the testing, it only means the Scrum team didn’t finish the testing. Scrum counts on everyone to do their part. Whenever any is needed, the people with those skills take the lead, but they all have to do their part.

answered 2010-06-24T16:47:22.680